Zelan Berhad (“ZB”) wishes to announce that on 3 September 2012, its wholly owned subsidiary, Zelan Construction Sdn Bhd, has been awarded by Mudajaya Corporation Berhad (“Mudajaya”) the subcontract for the engineering design and construction works of the following structures for the development of Tanjung Bin’s 1 x 1,000MW Coal Fired Plan Project in Negeri Johor Darul Takzim:

(a) Cooling water intake;

(b) Cooling water filtration and pump station; and

(c) Offshore water discharge culverts;

for the lump sum amount of Ringgit Malaysia Two Hundred Fifteen Million Two Hundred Fifty Thousand (RM215,250,000.00) only.

The commencement date for the abovementioned works is 3 September 2012 and the completion date is 15 August 2014.

Further to the Announcements made by ZB on 28 October 2011, 18 July 2012 and 2 August 2012, this is the second subcontract which has been awarded by Mudajaya to ZB in relation to the development of Tanjung Bin’s 1 x 1,000MW Coal Fired Plan Project.

This Announcement is dated 3 September 2012.

 